Guantanamo.- The Antonio Guiteras Thermal Power Plant has successfully completed a hydraulic test at 120 bar, with no leaks detected. The result marks a key step in the protocol ahead of the plant’s startup.

Following the successful test, workers removed the scaffolding and began sealing the boiler, the plant reported through its official channels.

Engineer Elmer García Romero, the plant’s deputy technical director, confirmed that the hydraulic and pneumatic tests and the metallographic inspection of the welds were all completed successfully. “A tense Sunday ends with good news,” the plant said in its report.

With testing complete, workers expect to spend nearly two hours sealing the access points and finishing the remaining tasks. They will then ignite the boiler and continue the startup process until the unit synchronizes with the grid, potentially in the early hours of Monday.

The startup team is prepared to oversee the next phase, bringing the Antonio Guiteras plant closer to rejoining the National Electric System.

Source: Cubadebate